How to Quote Demolition Jobs: Trade Insights on Waste & Labour

5 min read

Accurate demolition quoting balances four cost drivers: labour hours, equipment time, waste volume, and disposal fees. Professional Gold Coast and Brisbane strip out crews use square metre rates for standard work, then add line items for variables like access difficulty, asbestos risk and substrate grinding. A reliable fixed-scope quote should itemise each component so the client and contractor agree on exactly what is included before work starts.

The Four Cost Drivers

1. Labour Hours

Labour is typically the largest cost component:

  • Crew rate: AUD 80 to 150 per hour per worker
  • Typical small job crew: 2 workers
  • Typical commercial defit crew: 3 to 6 workers

A 4-hour bathroom demo with 2 workers represents AUD 640 to 1,200 in labour alone.

2. Equipment Time

Specialised equipment is costed by hour or day:

EquipmentHire/Use Rate
Diamond grinderAUD 200 to 400 per day
Ride-on scraperAUD 400 to 700 per day
Chipping hammer with extractionAUD 100 to 200 per day
HEPA industrial vacuumAUD 100 to 200 per day
Skip bin (4 cubic metre)AUD 350 to 500
Skip bin (8 cubic metre)AUD 600 to 900

3. Waste Volume

Estimate waste in cubic metres:

Job TypeTypical Waste Volume
Small ensuite1 to 2 cubic metres
Family bathroom2 to 4 cubic metres
Kitchen2 to 5 cubic metres
Single room (40 sqm) flooring removal1 to 3 cubic metres
Full house strip out8 to 20 cubic metres
Commercial floor (300 sqm)10 to 25 cubic metres

4. Disposal Fees

Queensland disposal levies as of 2026:

  • General construction waste: AUD 75 to 105 per tonne
  • Mixed waste: AUD 90 to 120 per tonne
  • Asbestos: AUD 200 to 400 per tonne plus handling

Always check current rates with your local waste facility.

Square Metre Rates by Service Type

Industry-standard pricing on the Gold Coast and Brisbane:

ServiceRate per sqm
Carpet removalAUD 8 to 15
Vinyl removal with adhesiveAUD 15 to 30
Timber/bamboo floor removalAUD 25 to 45
Tile removal (residential)AUD 30 to 60
Tile removal (commercial heavy)AUD 40 to 80
Concrete grinding (light)AUD 25 to 45
Concrete grinding (epoxy/heavy)AUD 40 to 80
Wall lining removalAUD 20 to 40
Ceiling lining removalAUD 25 to 50

Comparison: Quoting Approaches

ApproachProsCons
Hourly rateFlexibleRisk of scope creep, surprise costs
Square metre ratePredictable per areaDoesn't account for unique conditions
Fixed-scope itemisedClear, no surprisesRequires thorough site assessment
Cost-plusTransparentRequires trust and documentation

The fixed-scope itemised approach is best for client-contractor relationships and accuracy.

The Itemised Quote Format

A professional quote should include:

  1. Site address and contact details
  2. Scope of works (each task as separate line item)
  3. Square metre measurements for each component
  4. Quantity of fixtures or items removed
  5. Labour hours estimate
  6. Equipment included
  7. Waste disposal included
  8. Exclusions (clearly listed)
  9. Variations process (how changes are handled)
  10. Payment terms
  11. Insurance certificates available on request
  12. Validity period (usually 30 days)

Common Quoting Mistakes

Underestimating Substrate Issues

Multi-layer flooring, thick mortar bedding, or hidden adhesive can double the time on the floor portion. Always inspect cores or get photos before quoting blind.

Skipping Asbestos Risk Pricing

Pre-1990 homes have asbestos potential. Either include "asbestos testing AUD 350 if required" or quote contingent on no asbestos.

Forgetting Access Time

Small lifts, tight stairs, parking issues add 10 to 30 percent labour time. Include site assessment access notes in the quote.

Underpricing Disposal

Disposal levies have increased significantly. Use current rates, not historical estimates.

No Contingency for Hidden Issues

Add 5 to 10 percent contingency to absorb minor unknowns. Larger surprises (structural damage, asbestos) trigger variations.

Sample Bathroom Demolition Quote Structure

SCOPE:

  • Remove all fixtures (vanity, toilet, shower, bath, tapware): AUD 350
  • Remove wall tiles and bedding (12 sqm at AUD 50/sqm): AUD 600
  • Remove floor tiles and bedding (6 sqm at AUD 60/sqm): AUD 360
  • Remove existing waterproofing membrane: AUD 150
  • Concrete grinding for substrate prep: AUD 280
  • Skip bin and waste disposal (4 cubic metres): AUD 450
  • HEPA vacuum and final clean: included
  • Site protection and containment: included

SUBTOTAL: AUD 2,190 GST: AUD 219 TOTAL: AUD 2,409

EXCLUDES:

  • Plumbing isolation (separate licensed trade)
  • Electrical isolation (separate licensed trade)
  • Asbestos testing or removal (if discovered)

TIMELINE: 1 day START DATE: confirmed within 24 hours of acceptance PAYMENT: 30% deposit, balance on completion

Why This Matters for Clients

When you receive a vague single-line quote like "Bathroom demolition: AUD 2,000" you have no way to:

  • Compare with another quote
  • Identify what's missing
  • Negotiate specific items
  • Hold the contractor to scope

Always request itemised quotes. Reputable contractors provide them on request.

Get a Detailed Itemised Quote

Strip It Out provides itemised, fixed-scope quotes for every Gold Coast and Brisbane project. Send photos and dimensions for a same-day quote. Call 0430 030 633.

Ready to get started?

Contact our friendly team for a free, no-obligation quote. We service the Gold Coast, Brisbane, and surrounding areas 7 days a week.